Strike action in circumstances where there has been a long delay between the issuing of a certificate of outcome and the subsequent election to embark on a strike
PRASA t/a Metrorail v SATAWU and Others (C190/2016)
ISSUE
Whether a strike is protected in circumstances where there has been an unreasonably long delay between the issuing of a certificate of outcome and the subsequent election to embark upon strike action.
COURT’S DECISION
In PRASA t/a Metrorail v SATAWU and Others (C190/2016), a decision handed down by the Labour Court on 12 May 2016, the court was faced with the deciding whether strike action embarked upon by SATAWU was legal or not. Werksmans represented PRASA in the dispute and successfully argued that the strike action should be regarded as unprotected.
In September 2014 SATAWU referred a dispute of mutual interest to the Commission for Conciliation, Mediation and Arbitration (“CCMA”). SATAWU demanded that PRASA, in the Western Cape, absorb all fixed term employees on a permanent basis and conclude salary parity in all departments in the region. The dispute was unresolved and on 21 October 2014 a certificate of outcome was issued.
Upon receiving the certificate of outcome SATAWU elected not to engage in strike action. To the contrary, they engaged in on-going negotiations with PRASA on both a regional and national level regarding, among others, the issues forming the subject matter of the certificate. On 4 April 2016, some 18 months later, SATAWU gave notice of its intention to embark upon strike action on 6 April 2016.
The Court held that the demand that all fixed term employees be made permanent was no longer a demand of mutual interest by virtue of the enactment of section 198B(3) of the Labour Relations Act 66 of 1995, as amended (“LRA”). This section deals with the fact that, absent just cause, a fixed term employee who is employed on a temporary basis for a period of three months is regarded as being employed on a permanent basis and has therefore rendered this an issue of right, not of mutual interest.
The court also gave consideration to the argument that by SATAWU failing to embark upon strike action and by continuing negotiations, SATAWU could be said to have waived, estopped or abandoned their right to strike.
In having regard to prior case law the Court held that:
The inquiry should not centre on a waiver of the right to strike. Rather, it is a failure to rely on a specific certificate of outcome that is discernible in a case such as that before [the court]…the right to strike is retained, but after an unreasonable delay in acting on the issuing of a certificate, a union is required to go through the procedural steps set out in section 64 of the LRA once more. This approach accords with the speedy resolution of disputes on which the LRA is premised. It is also imminently sensible: over a period of 18 months there are likely to have been charges in the collective bargaining relationship. The procedural requirements clothing strike action with protection, which include the opportunity for parties to reach a settlement agreement through the conciliation process, may produce a different outcome, given the effluxion of time”.
IMPORTANCE OF THIS CASE
This case is a further reiteration of the need for a speedy resolution to disputes in terms of the LRA. It requires a consideration of the particular facts of a matter to determine whether, in the particular circumstances, there has been an unreasonable delay between the issuing of a certificate of outcome and the embarking upon strike action. This is a factual question. Should this be found to be the case, then the union concerned must once again follow the steps required by the law before embarking on strike action.
Click on the link if you’ like to more information on Werksmans expertise in the Labour & Employment sector.
Latest News
Ten things you need to know about price gouging: The state of play in South Africa
By Paul Coetser, Director and Head of the Competition practice The Competition Commission is aggressively pursuing any company alleged to [...]
COVID-19 regulations and how commercial landlords may survive
by Walid Brown, Director and Elzaan Haynes, Candidate Attorney The COVID-19 national lockdown restrictions (" the lockdown restrictions") are having [...]
Medical Schemes Act Amendment: COVID-19 declared a PMB
by Neil Kirby, Director and Head of the Healthcare & Life Sciences practice and Zamathiyane Mthiyane, Senior Associate Pursuant to a [...]
COVID-19 Temporary Employer / Employee Relief Scheme (“TERS”) applications for May
by Jacques van Wyk, Director and Thabisa Yantolo, Candidate Attorney Employers who are registered with the Unemployment Insurance Fund ("UIF"), [...]
‘Special measures’ for the return to work of employees older than 60 years old
by Jacques van Wyk Director and Thabisa Yantolo, Candidate Attorney On 29 April 2020 the Minister of Cooperative Governance and [...]
New directions, regulations and a Labour Court judgment bring clarity to the mining industry
by Chris Stevens, Director and Head of the Mining, Environmental & Resources practice; Kathleen Louw, Director; Bronwyn Parker, Senior Associate; [...]