Thank you energy minister, now let’s hurry
Former Energy Minister Jeff Radebe has at last told the National Energy Regulator of South Africa (Nersa) to license applications from businesses allowing them to generate their own power and feed it into the national grid.
Radebe’s welcome move will certainly help in alleviating electricity supply constraints as it opens the generation market to allow the private sector to provide power together with Eskom.
But more needs to be done – and in a hurry to prevent the lights going out again.
Nersa is only allowed to license applications from industrial, agricultural, mining and similar businesses to generate their own capacity for projects between 1 megawatt (MW) and 10MW – without waiting for the promulgation of the new Integrated Resource Plan (IRP) which has been under discussion by the National Economic Development and Labour Council (Nedlac) for many years.
It shows what can be done when you work around the lack of progress that has hampered Nedlac for so long now. The draft IRP, tabled in August 2018, is likely to take several more months before consultation is complete.
But the newly appointed Minister needs to go even further to allow smaller generation by businesses and households that want to produce energy, mostly for their own use. Typically these entities would produce up to 1MW and will need to be registered. Nersa expects to be able to register these entities within the next two to three months.
But this is where they need to hurry, provide clarity and get this administrative hurdle out of the way.
As winter approaches, South Africa’s economy cannot afford to wait for months on end for these smaller projects to be approved. The morale of the country is also important and it would be real proof of government’s new broom election promise for there to be fewer blackouts (ideally no blackouts at all)- and demonstrable steps to a long term solution.
Fortunately, households producing less than 100 kilowatts (kWh), typically by way of solar panels, do not need to register with Nersa.
Latest News
Electric vehicle tax incentive: what electric vehicle manufacturers should know
Reviewed by Natalie Scott, Director and Head of Sustainability On 24 December 2024, Cyril Ramaphosa, the President of the [...]
Are raising fees similar to interest?
The tax court, in a reportable judgment handed down on 13 January 2025, considered whether raising fees are finance charges [...]
National Minimum Wage Increases For 2025
With effect from 1 March 2025, the national minimum wage will be adjusted to R28.79 for each ordinary hour worked. [...]
Housing consumer rights headed in the right direction
Assisted by Alexi Andropoulos, Candidate Attorney On Monday, 27 January 2025, while global news headlines flooded with the Expropriation Bill [...]
Expropriation Act: Deconstructed and Demystified
President Cyril Ramaphosa signed the Expropriation Bill into law on 23 January 2025. The newly assented to Expropriation Act No. [...]
Breaking News – Supreme Court of Appeal Rules on Voting Rights of Post-Commencement Creditors in Business Rescue in Landmark Judgment
The Supreme Court of Appeal (SCA) in Mashwayi Projects (Pty) Ltd v Wescoal Mining (Pty) Ltd has delivered a significant [...]