Update: Directions on resumption of maintenance and construction of energy projects
by Nozipho Bhengu, Director
The regulations issued in terms of the Disaster Management Act, 2020 (“Regulations“), which set out the relaxation of the lockdown restrictions under Alert Level 4, permitted the resumption of civil engineering services for public works projects (including water, energy and sanitation) and public works civil engineering and construction works. In order to provide certainty as to the specific services covered by the Regulations, on 15 May 2020 the Department of Mineral Resources and Energy published directions under the Government Notice No. 542(“Directions“) which provided much needed clarity as to which “civil engineering activities for public works” relating to energy and other additional services are permitted to recommence and continue under Alert Level 4. These specifically include:
- “Civil engineering for public works projects” in so far as it relates to energy, including the following:
(i) projects procured under the Renewable Energy Independent Power Producers Procurement Programme that are currently in construction;
(ii) embedded generation projects under construction and listed in Schedule 2 to the Electricity Regulation Act, 2006 (Act No. 4 of 2006) or licensed in terms of section 7 (1) of the Electricity Regulation Act;
(iii) Eskom new build programme which includes Medupi and Kusile;
(iv) the Department of Mineral Resources and Energy national sodas solar water heater programme and projects;
(v) energy efficiency and demand side management projects;
(vi) national electrification programme;
(vii) liquid fuels (including retails) projects under maintenance and construction;
(viii) liquid Petroleum Gas projects under maintenance and construction; and
(ix) nuclear projects under maintenance and construction in power stations and other nuclear facilities.
In addition, the above, the Directions also confirmed that the following services are permitted under Alert Level 4:
- all professional entities that provide licences, approvals and authorisations for the maintenance and construction of energy projects;
- all professional planning, costing and design work that supports construction work on sites, in anticipation of incremental work on construction sites;
- contracted suppliers, contractors and consultants who need to travel across borders to attend to projects; and
- energy construction work for already priced and awarded government tenders.
Latest News
South Africa: Merger Notification Thresholds and Filing Fees Increase from 1 May 2026
by Ahmore Burger-Smidt, Director and Head of Regulatory and Raisah O Mahomed, Associate South Africa's Minister of Trade, Industry and [...]
“Corporate Death by Winding-Up”: Pretoria High Court Reaffirms the Badenhorst Principle
by Eric Levenstein, Director and Head Insolvency & Business Rescue, Amy Mackechnie, Senior Associate and Clio Patricios, Candidate Attorney A [...]
South Africa’s Information Regulator: What the 2025/26 Annual Performance Plan means for Business (as presented to the Portfolio Committee on 5 May 2026
by Ahmore Burger-Smidt, Director and Head of Regulatory “It is only the inner sanctum of a person, such as his/her [...]
Urgency misconceived: A cautionary note on process, principle and professional responsibility
by Bradley Workman-Davies, Director The decision in Wheatley v Commission for Conciliation, Mediation & Arbitration & others (2026) 47 ILJ [...]
Digital taxes are reshaping cross-border e-commerce economics in Africa
by Tebogo Sibidla, Director Digital taxation has moved from policy debate to regulatory reality. Governments across the world are implementing [...]
A safe voice or silent risk: An attempt at reforming whistleblower protection through the Protected Disclosures Draft Bill
by Harold Jacobs, Director, Luyanda Lebepe, Senior Associate and Kian Steytler, Candidate Attorney The case of Babita Deokaran, a senior [...]