Update: Directions on resumption of maintenance and construction of energy projects
by Nozipho Bhengu, Director
The regulations issued in terms of the Disaster Management Act, 2020 (“Regulations“), which set out the relaxation of the lockdown restrictions under Alert Level 4, permitted the resumption of civil engineering services for public works projects (including water, energy and sanitation) and public works civil engineering and construction works. In order to provide certainty as to the specific services covered by the Regulations, on 15 May 2020 the Department of Mineral Resources and Energy published directions under the Government Notice No. 542(“Directions“) which provided much needed clarity as to which “civil engineering activities for public works” relating to energy and other additional services are permitted to recommence and continue under Alert Level 4. These specifically include:
- “Civil engineering for public works projects” in so far as it relates to energy, including the following:
(i) projects procured under the Renewable Energy Independent Power Producers Procurement Programme that are currently in construction;
(ii) embedded generation projects under construction and listed in Schedule 2 to the Electricity Regulation Act, 2006 (Act No. 4 of 2006) or licensed in terms of section 7 (1) of the Electricity Regulation Act;
(iii) Eskom new build programme which includes Medupi and Kusile;
(iv) the Department of Mineral Resources and Energy national sodas solar water heater programme and projects;
(v) energy efficiency and demand side management projects;
(vi) national electrification programme;
(vii) liquid fuels (including retails) projects under maintenance and construction;
(viii) liquid Petroleum Gas projects under maintenance and construction; and
(ix) nuclear projects under maintenance and construction in power stations and other nuclear facilities.
In addition, the above, the Directions also confirmed that the following services are permitted under Alert Level 4:
- all professional entities that provide licences, approvals and authorisations for the maintenance and construction of energy projects;
- all professional planning, costing and design work that supports construction work on sites, in anticipation of incremental work on construction sites;
- contracted suppliers, contractors and consultants who need to travel across borders to attend to projects; and
- energy construction work for already priced and awarded government tenders.
Latest News
The validity of automatic termination clauses in contracts of employment
ISSUE(S) Whether the employee was unfairly dismissed after his appointment letter was automatically terminated because of a provision stating [...]
Holding onto land: the regulation of Agricultural Land Holdings Bill
INTRODUCTION During the 2016 State of the Nation Address, the president of the Republic of South Africa first announced [...]
And now for something completely different (or not?)
INTRODUCTION With effect from 1 June 2017 the Medicines and Related Substances Amendment Act No. 72 of 2008 ("the [...]
Director, Nastascha Harduth, becomes the first female fellow of INSOL international in SA
The on-going global financial crisis, recent confirmation by STATSSA that South Africa is in a technical recession and the globalization [...]
It’s not me, it’s you: incompatibility as a ground for dismissal
"An employer has the prerogative to set reasonable standards pertaining to the harmonious interpersonal relationships in the workplace" – words [...]
The binding nature of collective agreements on minority unions
ISSUE(S) Whether a collective agreement concluded between a majority union and an employer, but extended to a minority union, [...]