Update: Directions on resumption of maintenance and construction of energy projects
by Nozipho Bhengu, Director
The regulations issued in terms of the Disaster Management Act, 2020 (“Regulations“), which set out the relaxation of the lockdown restrictions under Alert Level 4, permitted the resumption of civil engineering services for public works projects (including water, energy and sanitation) and public works civil engineering and construction works. In order to provide certainty as to the specific services covered by the Regulations, on 15 May 2020 the Department of Mineral Resources and Energy published directions under the Government Notice No. 542(“Directions“) which provided much needed clarity as to which “civil engineering activities for public works” relating to energy and other additional services are permitted to recommence and continue under Alert Level 4. These specifically include:
- “Civil engineering for public works projects” in so far as it relates to energy, including the following:
(i) projects procured under the Renewable Energy Independent Power Producers Procurement Programme that are currently in construction;
(ii) embedded generation projects under construction and listed in Schedule 2 to the Electricity Regulation Act, 2006 (Act No. 4 of 2006) or licensed in terms of section 7 (1) of the Electricity Regulation Act;
(iii) Eskom new build programme which includes Medupi and Kusile;
(iv) the Department of Mineral Resources and Energy national sodas solar water heater programme and projects;
(v) energy efficiency and demand side management projects;
(vi) national electrification programme;
(vii) liquid fuels (including retails) projects under maintenance and construction;
(viii) liquid Petroleum Gas projects under maintenance and construction; and
(ix) nuclear projects under maintenance and construction in power stations and other nuclear facilities.
In addition, the above, the Directions also confirmed that the following services are permitted under Alert Level 4:
- all professional entities that provide licences, approvals and authorisations for the maintenance and construction of energy projects;
- all professional planning, costing and design work that supports construction work on sites, in anticipation of incremental work on construction sites;
- contracted suppliers, contractors and consultants who need to travel across borders to attend to projects; and
- energy construction work for already priced and awarded government tenders.
Latest News
Sexual harassment in the workplace – a balanced consideration
By Bradley Workman-Davies, Director and Kelly Sease, Candidate Attorney On 18 March 2022, the Minister of Employment and Labour (“Minister“) [...]
ChatGPT: Yet Another Hurdle for Data Privacy?
Data Privacy & Cybercrime ChatGPT is an OpenAI[1] developed artificial intelligence (AI) chatbot which has been programmed to have advanced conversational [...]
When your data depository and platform are the biggest, competition law becomes important or a problematic weapon!
"...In so doing, Google has engaged in exclusionary conduct that has severely weakened, if not destroyed, competition in the ad [...]
The Twitter data hack
Data Privacy & Cybercrime by Ahmore Burger-Smidt, Head of Regulatory Practice and Chiara Ferri, Candidate Attorney In the first week [...]
Re-inventing the wheel or balancing the scales?
Digitalisation, globalisation and the COVID-19 pandemic have made certain online platforms (along with their products and services) integral to the [...]
The myth of consent: Big tech meets (big) data protection
Data Privacy & Cybercrime Consumers rely on digital platforms such as Google, Amazon and Takealot to gain wider and more [...]