Update: Directions on resumption of maintenance and construction of energy projects
by Nozipho Bhengu, Director
The regulations issued in terms of the Disaster Management Act, 2020 (“Regulations“), which set out the relaxation of the lockdown restrictions under Alert Level 4, permitted the resumption of civil engineering services for public works projects (including water, energy and sanitation) and public works civil engineering and construction works. In order to provide certainty as to the specific services covered by the Regulations, on 15 May 2020 the Department of Mineral Resources and Energy published directions under the Government Notice No. 542(“Directions“) which provided much needed clarity as to which “civil engineering activities for public works” relating to energy and other additional services are permitted to recommence and continue under Alert Level 4. These specifically include:
- “Civil engineering for public works projects” in so far as it relates to energy, including the following:
(i) projects procured under the Renewable Energy Independent Power Producers Procurement Programme that are currently in construction;
(ii) embedded generation projects under construction and listed in Schedule 2 to the Electricity Regulation Act, 2006 (Act No. 4 of 2006) or licensed in terms of section 7 (1) of the Electricity Regulation Act;
(iii) Eskom new build programme which includes Medupi and Kusile;
(iv) the Department of Mineral Resources and Energy national sodas solar water heater programme and projects;
(v) energy efficiency and demand side management projects;
(vi) national electrification programme;
(vii) liquid fuels (including retails) projects under maintenance and construction;
(viii) liquid Petroleum Gas projects under maintenance and construction; and
(ix) nuclear projects under maintenance and construction in power stations and other nuclear facilities.
In addition, the above, the Directions also confirmed that the following services are permitted under Alert Level 4:
- all professional entities that provide licences, approvals and authorisations for the maintenance and construction of energy projects;
- all professional planning, costing and design work that supports construction work on sites, in anticipation of incremental work on construction sites;
- contracted suppliers, contractors and consultants who need to travel across borders to attend to projects; and
- energy construction work for already priced and awarded government tenders.
Latest News
Strike action in circumstances where there has been a long delay between the issuing of a certificate of outcome and the subsequent election to embark on a strike
PRASA t/a Metrorail v SATAWU and Others (C190/2016) ISSUE Whether a strike is protected in circumstances where there has [...]
Is length of service reason to pay different salaries to employees performing the same functions?
Pioneer Foods (Pty) Ltd v Workers Against Regression (WAR) & others ISSUE Whether length of service is a [...]
Is a trade union entitled to organisational rights in terms of the LRA after acquiring majority representation at a single branch?
Professional Transport and Allied Workers Union obo members / Professional Aviation Services [2016] 4 BALR 421 ISSUE Whether a [...]
Asset for share transactions – beware of selling your shares within 18 months especially in the context of a share buy-back
To prevent tax considerations from discouraging the incorporation of a business, a specific form of ‘rollover relief’ is available when an asset [...]
A new era dawns – criminalisation of cartel conduct
On 22 April 2016, a Presidential Proclamation (“Proclamation”) appeared in the Government Gazette which confirmed that the provisions contained in [...]
The employer’s responsibility during the transfer of an employee
Senne and others v Fleet Africa [2016] ZALCJHB 48 ISSUE One of the automatic consequences of a transfer in [...]