Legal updates and opinions
News / News
Update: Directions on resumption of maintenance and construction of energy projects
by Nozipho Bhengu, Director
The regulations issued in terms of the Disaster Management Act, 2020 (“Regulations“), which set out the relaxation of the lockdown restrictions under Alert Level 4, permitted the resumption of civil engineering services for public works projects (including water, energy and sanitation) and public works civil engineering and construction works. In order to provide certainty as to the specific services covered by the Regulations, on 15 May 2020 the Department of Mineral Resources and Energy published directions under the Government Notice No. 542(“Directions“) which provided much needed clarity as to which “civil engineering activities for public works” relating to energy and other additional services are permitted to recommence and continue under Alert Level 4. These specifically include:
- “Civil engineering for public works projects” in so far as it relates to energy, including the following:
(i) projects procured under the Renewable Energy Independent Power Producers Procurement Programme that are currently in construction;
(ii) embedded generation projects under construction and listed in Schedule 2 to the Electricity Regulation Act, 2006 (Act No. 4 of 2006) or licensed in terms of section 7 (1) of the Electricity Regulation Act;
(iii) Eskom new build programme which includes Medupi and Kusile;
(iv) the Department of Mineral Resources and Energy national sodas solar water heater programme and projects;
(v) energy efficiency and demand side management projects;
(vi) national electrification programme;
(vii) liquid fuels (including retails) projects under maintenance and construction;
(viii) liquid Petroleum Gas projects under maintenance and construction; and
(ix) nuclear projects under maintenance and construction in power stations and other nuclear facilities.
In addition, the above, the Directions also confirmed that the following services are permitted under Alert Level 4:
- all professional entities that provide licences, approvals and authorisations for the maintenance and construction of energy projects;
- all professional planning, costing and design work that supports construction work on sites, in anticipation of incremental work on construction sites;
- contracted suppliers, contractors and consultants who need to travel across borders to attend to projects; and
- energy construction work for already priced and awarded government tenders.
Latest News
Claims by employee for costs of Covid-19 tests cannot be referred to the CCMA
Basic Conditions of Employment Act ("BCEA') threshold by Jacques van Wyk, Director and Andre van Heerden, Senior Associate Issue Whether [...]
Code of conduct of the Banking Association of South Africa: What we know
Codes of conduct focused on the processing of personal information by Ahmore Burger-Smidt, Director and Head of Data Privacy and [...]
National Health Insurance Bill
National Health Insurance (NHI) Bill National Health Insurance: Quo Vadis? by Neil Kirby, Director: Healthcare & Life Sciences Law, Werksmans [...]
The application of the reportable arrangement provisions to contributions to offshore discretionary trusts
Offshore discretionary trusts by Erich Bell, Director Werksmans Tax Proprietary Limited The reportable arrangement provisions in Part B of Chapter [...]
The existence of a disputed arbitration agreement: Whose call?
Arbitration agreement by Pierre Burger, Director Arbitration is a consensual process – it depends on an agreement between the parties [...]
Swanepoel v KPMG Services (Pty) Ltd (J494/19) [2021] ZALCJHB 457 (13 December 2021)
Termination of the employment relationship in terms of the UI-19 by Bankey Sono, Director and Neo Sewela, Candidate Attorney Very [...]